  1. E

    what is the procedure for quantity calculation for

    Thank you !! From your experience and point of view can you please provide the percentage of wastage to be added on estimation for cement, sand, aggregate, steel, tiles etc of construction materials.
  2. E

    If footing Concrete done with grade of concrete m30 cube test fail at 28 days., what to do next proceed

    If your 28days cube fails then you can go for additional test like rebound hammer/core cutting/ultra sonic test. But still it fails on those tests the work may rejected and additional strengthening of the structure shall be considered.