We prefer 3 stage crusher. First stage is jaw and second stage is cone then 3rd stage is VSI is better. The quality of Crusher sand will be increase and 20mm and 10mm aggregates shape will be better i.e. Reduce the flakiness and Elongation Index values. For road projects it is mandatory.
Generally Cracks shall be develop in between initial and final setting time of concrete. In this time late finishing will help for not increasing the crack width. Separate manpower to be deployed for late finishing.
Protection of concrete after final setting time to 24 hours is important.
How many sets of props, side shuttering and slab shuttering required for 3 days cycle?
de-shuttering of slab shuttering depends on span and type of cement used.
3 days cycle is very difficult in practical but 6 to 7 days is okay.