Recent content by MAHESWAR KABI

  1. M

    What is cause of Honeycombing and cavities in this column concrete

    poor supervision work & poor shuttering work , that's enough ...
  2. M

    Information about lapping zones in columns and beams

    Generally 50D we use in lapping in site . Some specially cases we 57D also used .
  3. M

    What is wrong in this RCC structure construction?

    there are concrete between polythene , which is not good for future . Another point is PCC is not provided under plinth beam.