Security deposit deducted at 5 percent from contractors bill is -

Dnyan Deshmukh

Staff member
Security deposit deducted at 5 percent from contractors bill is -

(a) refunded when the contractor has completed the work

(b) refunded even before the completion of the work provided good progress has been established

(c) retained till the expected life of the structure of say 100 years and spent for maintenance

(d) refunded when the defect liability period of six months or one monsoon whichever in later is over.

The correct Answer Is
(d) refunded when the defect liability period of six months or one monsoon whichever in later is over
 
  • Like
Reactions: Sumit Civil
Security deposit deducted at 5 percent from contractors bill is -

(a) refunded when the contractor has completed the work

(b) refunded even before the completion of the work provided good progress has been established

(c) retained till the expected life of the structure of say 100 years and spent for maintenance

(d) refunded when the defect liability period of six months or one monsoon whichever in later is over.
Option D is correct answer.
 

AjitA

Newbie
Security deposit deducted at 5 percent from contractors bill is -

(a) refunded when the contractor has completed the work

(b) refunded even before the completion of the work provided good progress has been established

(c) retained till the expected life of the structure of say 100 years and spent for maintenance

(d) refunded when the defect liability period of six months or one monsoon whichever in later is over.
a