A CPM network is to be drawn considering -

Dnyan Deshmukh

Staff member
A CPM network is to be drawn considering -

(a) activity sequencing without resource availability

(b) least direct cost durations for activities

(c) least total cost durations for activities

(d) activity sequencing considering resources availability for each individual for activity separately.

The correct Answer Is
(d) activity sequencing considering resources availability for each individual for activity separately