GAP & Risk of Indenting Process in Construction, Do you agree?

Do you Agree with Above


  • Total voters
    3

GAP

Risk

No Process to intimate the material requirements for contractors to site engineers for the next month in advance

Delays in work initiation & completion by contractors

No Document Format to request requirement of materials by contractors to site engineers

No records & audit trail is created for actual quantity of material requested by contractors to perform the job.

Approval matrix for timeliness of indenting process needs to be defined

Less accountability
Results to delay in work and procurement


Reduction of Timeliness on indent approval process

Delays in approvals
Delays in work initiation & completion results in incurring higher finance costs on borrowed funds


Tolerance % not defined in Material Master

The system will not be able to calculate rejections
Vendor Evaluation could not be performed


Timeliness for the closing of open Indent in In4Suite not defined

Results in procurement against open indents

System does not capture date of approval of Indent by Site Head in the Manual Register

Key KPI of delay in preparing indent by inventory team cannot be calculated