I'm preparing for an exam!

I need the answer... Can anyone please help me solving this?
Total float 10 days
Free float 5 days
Duration 4 days
Determine the maximum delay in starting time relative to the earliest start time that will allow all immediately succeeding activities to be scheduled anywhere between their earliest and latest completion times?