Labour Productivity Analysis for Mivan Formwork and Reinforcement Works

Sumit Civil

Well-Known Member
Doing the productivity analysis is important to achieve the cycle time of work for completion of project in time.

Labour Productivity Analysis.jpg

I have attached excel sheet for doing productivity analysis of labours for achieving cycle time in Mivan Formwork.
This will give you idea on how much time it will take to complete the cycle with available workforce and how much extra labours required to achieve required cycle time for doing Mivan shuttering and Reinforcement Works.

Excel sheet is attached below.
 

Attachments

  • Mivan productivity analys.XLS
    50 KB · Views: 2,361
  • Like
Reactions: Mangesh korpe
How many sets of props, side shuttering and slab shuttering required for 3 days cycle?
de-shuttering of slab shuttering depends on span and type of cement used.
3 days cycle is very difficult in practical but 6 to 7 days is okay.