Manpower Productivity Estimation

Dear Sir,
This is a good enfo shared in this forum.
Kindly clear my queries as per the attached sheet.
1- how to decide production rate for items which are not mention in the sheet & also for the items mentioned in sheet?
2- How to decide the duration of completion of activity?
 
  • Like
Reactions: azhar15deen
kindly read in depth
regarding your question no 1 the rates to be decided according to the market rate prevailing in city.regarding item not mentioned. work it out on your own

2. regarding question no 2. the productivity mention..divide the qty by productivity you will get duration
 

Sujit

Junior Member
In this they given duration also...if we calculated duration as per productivity/ quantity then duration almost changes..what is correct duration then as per formula or which is given in sheet