What is the minimum curing period?

VIDHYA SAGAR

Senior Member
Nov 25, 2017
60
14
India
#2
Curing should be done for the hydration process of cement.
The maximum hydration of cement will be till 72 hours. (3 days).
So 3 days curing is must.
Normally we used to do the curing for 7 days.