As per IS code how many kilogram Steel used in 1 m cube

amd007

Elite Member
As per IS code how many kilogram Steel used in 1 m cube

1) Slab – 1% of the total volume of concrete
2) Beam – 2% of the total volume of concrete
3) Column – 2.5% of total volume of concrete
4) Footings – 0.8% of the total volume of concrete

For example, let us take RCC column with reinforcement requirement of 2.5 % of concrete volume then the weight of the steel required will be:

(2.5*7850)/(100*1) = 196.25 kg

https://ia800406.us.archive.org/1/items/gov.in.is.456.2000/is.456.2000.pdf pls download the code and go through for further details ;)
 
1) Slab – 1% of the total volume of concrete
2) Beam – 2% of the total volume of concrete
3) Column – 2.5% of total volume of concrete
4) Footings – 0.8% of the total volume of concrete

For example, let us take RCC column with reinforcement requirement of 2.5 % of concrete volume then the weight of the steel required will be:

(2.5*7850)/(100*1) = 196.25 kg

https://ia800406.us.archive.org/1/items/gov.in.is.456.2000/is.456.2000.pdf pls download the code and go through for further details ;)
Thanks