In PERT analysis the duration of the activities is taken as -

Dnyan Deshmukh

Staff member
In PERT analysis the duration of the activities is taken as -

(a) Optimistic Time

(b) Pessimistic Time

(c) Most Likely Time

(d) Expected Mean Time.

The correct Answer Is
(d) Expected Mean Time
 
  • Like
Reactions: Sumit Civil