In time cost optimization of a project, crashing is done -
(a) on all the activities
(b) on all the activities lying on the critical paths
(c) only on activities lying on the original critical paths and having flatter cost slopes
(d) on original critical activities and those become critical.
The correct Answer Is
(c) only on activities lying on the original critical paths and