Procurement plan.

Dnyan Deshmukh

Staff member
Procurement plan is just like the construction schedule or the procurement plan is incorporated in the schedule as the resource requirement.

Material procurement is dependent of many factors and mostly dependent on the lead time required for the delivery of the materials after giving the purchase order to a supplier or a manufacturer. the process of the ordering material may varies from company to company as per there policy like raising the purchase request, market study and finalizing the brands of materials, Quality approval process, lead time consideration etc.

So you need to prepare your own procurement plan as per the construction schedule for scheduled requirements as per plan as well as for unplanned procurement of materials.

Or Simply you can take a list of required procurements of Materials and equipment for your particular project and submit the data to planning department about the required budgets and lead time so that they will incorporate it in their plan for timely execution of construction activities.