The design period for a water supply project is taken as -
(a) 50 to 10 years
(b) 10 to 15 years
(c) 15 to 20 years
(d) 20 to 30 years.
The correct Answer Is
(d) 20 to 30 years
(a) 50 to 10 years
(b) 10 to 15 years
(c) 15 to 20 years
(d) 20 to 30 years.
The correct Answer Is
(d) 20 to 30 years