To avoid vaporisation in the pipe line, the pipe line over the ridge is laid such that it is not more than
(a) 2.4 m above the hydraulic gradient
(b) 6.4 m above the hydraulic gradient
(c) 10.0 m above the hydraulic gradient
(d) 5.0 above the hydraulic gradient
(e) none of the above.
The correct Answer Is
(b) 6.4 m above the hydraulic gradient