When a CPM network is to be updated one considers -
(a) only completed jobs to be outside the purviews
(b) ongoing works to be outside the purviews
(c) only substituted items
(d) ongoing works and any other substitutions.
The correct Answer Is
(d) ongoing works and any other substitutions
(a) only completed jobs to be outside the purviews
(b) ongoing works to be outside the purviews
(c) only substituted items
(d) ongoing works and any other substitutions.
The correct Answer Is
(d) ongoing works and any other substitutions