Work Checklist - Flyash Brick Masonry Works

Dnyan Deshmukh

Staff member
Flyash Brick Masonry Works
For doing a partition wall, we use flyash bricks.

Checklist of Flyash Brick Masonry Works, consist of following checkpoints in it;
  • Approved architectural drawings available on site
  • RCC slab surface is cleaned properly
  • Line out checked as per drawing (first layer )
  • Fish wire pulled through conduits and beam bottom cleared
  • RCC column/wall surface roughened /mortar dash applied
  • Wetting of bricks done prior to use
  • Mortar proportion as specified ( )
  • M.S. trays used for mortar mixing
  • Mortar used within 45 minutes after mixing
  • Independent scaffolding system done for masonry
  • Provision for door openings/ windows openings /hold fasts/architectural feature checked
  • For 150mm thick Wall R.C.C. band provided.
  • Staggering of brick joints ensured
  • Proper bond/ anchorage with cross wall checked
  • Masonry joints kept not more than 10mm
  • Racking of joints done
  • Rich mortar metal packing provided for RCC and masonry joint
  • Construction date marked on wall
  • Curing of masonry ensured minimum for 7 days.


Checklist for doing flyash brick masonry work is attached herewith.

Checklist is a important record it helps us in order to get work done correctly and it ensure we do not miss any point to check which is important from aspect of Quality of work.
Checklist attached herewith is just a sample provided for your reference, work carried out as per this procedure may have different sets of standards, material specifications, standard operating procedures and terms and conditions for doing that work. This all parameter or some parameter may not match with one you are executing at your Project.
Kindly use it as reference document only to create Checklist. You are free to modify edit, delete add any content in it and use it as per your requirement.
 