Work Procedure for planning and scheduling of Project
Purpose :
To document a procedure for planning and scheduling of Project.
Objective :
A plan is prepared so that the project is completed as per schedule.
Scope :
This procedure is applicable to the entire project that the company proposes to develop.
Responsibility :
Regional Manager (RM)
Project Manager (PM)
Quality Records
1. Construction Master Program
2. Detailed Program
3. Tender Documents
Associated Procedure
Pre – Construction Activities
Site Meetings
Procedure
Purpose :
To document a procedure for planning and scheduling of Project.
Objective :
A plan is prepared so that the project is completed as per schedule.
Scope :
This procedure is applicable to the entire project that the company proposes to develop.
Responsibility :
Regional Manager (RM)
Project Manager (PM)
Quality Records
1. Construction Master Program
2. Detailed Program
3. Tender Documents
Associated Procedure
Pre – Construction Activities
Site Meetings
Procedure
- Based on the size of a project, the Project Manager (PM) in consultation with the senior MANAGEMENT shall prepare a Construction Master Program
- The Construction Master Program shall indicate broadly the major activities of the project and the schedules for completion of these activities.
- Upon completion of the Construction Master Program, the PM shall decide whether to formulate a detailed Program for ease of project monitoring and control. All major activities mentioned in the Construction Master Program shall be broken down to the required level in the detailed Program.
- The detailed Program shall generally consist of, but may not be limited to, the following:
- Activity listings
- Bar chart indicating
- Schedule of shop drawings submission
- Schedule of construction drawings required
- Bar chart indicating
- Schedule of work
- Schedule of key dates
- Sub-contracting the activities
- Obtaining various statutory approvals that may be required for completion of the project which may include but may not be limited to the following:
- NOC from Chief Fire Officer
- Intimation of Disapproval (I.O.D)
- Commencement certificate at various stages
- Permission for temporary structures.
- Application for Labour License.
- P-Form requirements.
- Drainage Approval
- Drainage Completion Certificate.
- PWD elevator completion certificate
- Approval from Chief Fire Officer
- Occupation Certificate
- Water connection and permanent power connection.
- Fortnightly schedule of work.
- Based on the detailed Program, the PM shall review with the project team and the contractors the progress of construction on a regular basis.
- It shall be the responsibility of the PM to present a progress report for the site under his charge at the monthly progress review meeting. As deemed necessary; PM shall modify the detailed Program so as to meet any revised schedule dates in consultation with the Senior Management.
- The PM shall prepare tender documents based on the Construction Master Program , detailed Program and technical specifications. Generally tender documents shall be prepared for
- Civil works.
- Sanitary and plumbing works.
- Electrical works and
- Fire fighting works.
- Tendering procedure shall be followed to select the contractor for the job.
- Activity listings