Cement slurry

Hi All,

How to calculate for future consumption of cement slurry per cum there is any IS code where consumption is mentioned. or any thump rule for cement slurry calculation per cum of poured concrete ????

Factor which effect more consumption like height of pouring point, temperature etc
 

furkan56

Apprentice
Cement slurry is used only for priming the pipeline. You need to coat the internal of pipeline from the point of pouring to point of placing you can get the quantity of slurry by finding the volume of pipe from length of pipeline and diameter of pipe. Then you can make the slurry in the proportion of 1:6 one part of cement and 6 parts of water.

Thumb rule 4 bag per cubic meter of slurry.