For a given activity, the Optimistic time, pessimistic time and the most probable estimates are 5, 17, 8 days respectively. The Expected time is -

Dnyan Deshmukh

Staff member
For a given activity, the Optimistic time, pessimistic time and the most probable estimates are 5, 17, 8 days
respectively. The Expected time is -

(a) 8 days

(b) 9 days

(c) 10 days

(d) 15 days .

The correct Answer Is
(b) 9 days
 
  • Like
Reactions: Sumit Civil