For a given activity, the Optimistic time, pessimistic time and the most probable estimates are 5, 17, 8 days
respectively. The Expected time is -
(a) 8 days
(b) 9 days
(c) 10 days
(d) 15 days .
The correct Answer Is
(b) 9 days
respectively. The Expected time is -
(a) 8 days
(b) 9 days
(c) 10 days
(d) 15 days .
The correct Answer Is
(b) 9 days