archdevil Royal Member India Apr 7, 2018 #2 scrub the old joint. remov all the loose particles. apply "ntto bond" as per manufacturer specification Upvote 0 Downvote
scrub the old joint. remov all the loose particles. apply "ntto bond" as per manufacturer specification
Dnyan Deshmukh Staff member Pune Apr 7, 2018 #3 https://civil4m.com/threads/construction-joints-location-placing-and-preparation-procedure.1507/ https://civil4m.com/threads/site-engineers-should-not-make-this-mistake-in-rcc-structure.281/ Above threads will give you some information on it. There are two types of construction joints. In horizontal direction - comes in column and wall they need to be made rough by removing laitance from top of concrete or by inserting 20mm aggregates half way into the fresh concrete surface. Or can be done by removing laitance by water jet, when concrete starts setting initially. or can be done by making shear keys in the concrete surface. In vertical direction - comes in slabs and beams etc. Should be in a form of key Reactions: sudhir.abhi Upvote 0 Downvote
https://civil4m.com/threads/construction-joints-location-placing-and-preparation-procedure.1507/ https://civil4m.com/threads/site-engineers-should-not-make-this-mistake-in-rcc-structure.281/ Above threads will give you some information on it. There are two types of construction joints. In horizontal direction - comes in column and wall they need to be made rough by removing laitance from top of concrete or by inserting 20mm aggregates half way into the fresh concrete surface. Or can be done by removing laitance by water jet, when concrete starts setting initially. or can be done by making shear keys in the concrete surface. In vertical direction - comes in slabs and beams etc. Should be in a form of key