When we work at a construction project, if sequencing of activity is not done, then the project may land up in trouble.
I had created a sequence of construction activities for one of may project of residential building in past.
It will also help you to track the activities for purchase, start and completion status.

The sequence of construction activities include following;
  1. Foundation (including excavation, anti-termite & de-watering) Footing
  2. Plinth beams (including earth filling compaction rubble soling)
  3. Grade slab (including Damp Proof course) with anti - termite
  4. 1st floor column beams, slabs & all RCC items staircase, lifts, etc including conceal conduit pipes, junction,s fan hooks, sleeves etc.
  5. Civil Work for U. G. Tank (suction & static & pump room)
  6. Placing order for lift & follow up.
  7. 2nd floor column beam slabs & all RCC items including conceal conduit pipes, junctions, fan hooks, sleeves etc.
  8. Manufacturing blocks
  9. Manufacturing door frames & window sub frames
  10. 3rd floor columns beam slab & all RCC items including conceal etc. conduit pipes, junction boxes, fan hooks, sleeves etc.
  11. Ground floor external & internal block masonry with door frames window & conduit pipe & boxes
  12. RCC patlee work in brick work
  13. 4th floor column beam slab & all RCC items with all conceal elc. Pipe work, junctions, fan hooks, sleeves etc.
  14. Fixing precast jallis on ground floor
  15. 1st floor external & internal block masonry
  16. Patlee in brick wall.
  17. 1st floor door & window frames fixing
  18. Ground floor junction box & conduit placing
  19. Internal cement plaster & backing coat (for toilets of Ground floor)
  20. Re-plastering conceal pipe chasing work
  21. 5th floor column beams slabs & all RCC items with etc. Pipe work & junctions, fan hooks, sleeves etc.
  22. 2nd floor external & internal block/ brick masonry
  23. RCC patlee work
  24. 2nd floor door & window frames fixing
  25. Re-plastering chasing part of conduit work
  26. 1st floor junction box & conduit placing.
  27. Internal cement plaster & toilet backing coat for 1st floor
  28. Re-plaster chess part of wall
  29. Fixing Pre cast jali 1st floor
  30. 6th floor column beams slabs & all RCC items including etc. Conceal conduits, junction boxes, fan hooks, sleeves etc.
  31. 3rd floor external & internal block masonry
  32. RCC patlee work
  33. 3rd floor door & window frames fixing
  34. Placing junction box & conduit for 2nd floor
  35. Re-plastering chasing part of wall
  36. Fixing Pre cast jali 2nd floor.
  37. Internal cement plaster & (toilet backing coat for 2nd floor
  38. Construction of kitchen platform 1st floor.
  39. Flooring & Skirting in all rooms & excluding toilets of Gr. floor
  40. Fixing Pre cast jali 3rd floor
  41. 7th floor column beams slabs & all RCC items including conceal etc. conduits, junctions, fan hooks, sleeves etc.
  42. 4th floor door & frames fixing
  43. 4th floor external & internal block masonry
  44. RCC patlee work
  45. Construction of kitchen platform on 2nd floor
  46. Placing junction box & conduit for 3rd floor
  47. Chased part re-plastering
  48. Fixing Pre cast jali 4th floor
  49. Internal plaster & toilet backing coat for 3rd floor
  50. Kitchen platform on 3rd floor
  51. Flooring & skirting in all room & kitchen excluding, toilets on 1st floor
  52. Fixing Pre cast jali 5th floor
  53. 8th floor column beams slabs & all RCC items including conceal etc. conduits, junction boxes, fan hooks & sleeves etc.
  54. 5th floor door frames fixing
  55. Kitchen platform on 4th floor
  56. 5th floor external & internal block masonry
  57. RCC patlee work
  58. Placing junction box & conduit for 4th floor
  59. Chased part re-plastering
  60. Fixing Pre cast jali 6th floor
  61. Internal plaster & toilet backing coat for 4th floor.
  62. Flooring & skirting in all rooms & kitchen excluding toilets of 2nd floor
  63. Fixing Pre cast jali 7th floor.
  64. 9th floor column beams slabs & all RCC items (7th floor plaster to be finished) including conceal conduit pipes, junction boxes, fan hooks sleeves etc.
  65. 6th floor door frames & window frames fixing
  66. Kitchen platform on 5th floor.
  67. 6th floor external & internal block masonry
  68. RCC patlee work
  69. Placing junction box & conduit for 5th floor.
  70. Chased part re-plastering
  71. Fixing Pre cast jali 8th floor.
  72. Internal plaster & toilet backing coat for 1st 5 floor.
  73. Internal marble granite cladding & flooring for lobbies including polishing on Ground floor
  74. Floor & skirting in all rooms & kitchen excluding toilets of 3rd floor.
  75. Waterproofing of toilets/sumps 1st floor 1st base coat
  76. 10th floor columns beams slabs & all RCC items including etc. Conduit pipes, junction boxes, fan hooks sleeves etc.
  77. 7th floor door frames fixing fixing
  78. Kitchen platform on 6th floor
  79. 7th floor external & internal block masonry
  80. RCC patlee work
  81. Placing junction box & conduit for 6th floor.
  82. Chased part re-plastering
  83. Fixing Pre cast jali 9th floor.
  84. Internal plaster & toilet backing coat for 6th floor.
  85. Interior cladding & flooring & polishing in lobbies on 1st floor.
  86. Flooring & skirting in all rooms & Kitchen excluding toilets of 4th floor
  87. External plaster ground to 8th floor
  88. Fixing Pre cast jali 10th floor.
  89. 11th floor column beams slabs & all RCC items including conceal etc. conduit pipes, junction boxes, fan hooks & sleeve etc.
  90. Waterproofing of toilets/sumps on 2nd floor, Base coat
  91. 8th floor door frames fixing
  92. Kitchen plat form on 7th floor
  93. 8th floor external & internal block masonry
  94. RCC patlle work
  95. Fixing Pere cast jali 11th floor
  96. Internal plaster & toilet backing coat for 7th floor
  97. Interior cladding & flooring & polishing in lobbies on 2nd floor.
  98. flooring & skirting in all room & kitchen excluding toilets of 5th floor
  99. External plaster on 1st floor
  100. Laying concealed traps etc including making holes in masonry for pipes from 1st flr.
  101. Flooring & dado of toilets including polishing from 1st floor.
  102. Fixing of T.W. doors & window shutter 1st floor
  103. Fixing Pre cast jali 12th floor.
  104. 12th floor column beams slabs & all RCC items including conceal etc. conduit pipes, fan hooks, junction boxes, sleeves etc.
  105. External plaster 3rd floor
  106. Waterproofing of toilets/sumps on 3rd floor Base coat
  107. 9th floor door frames fixing masonry
  108. Kitchen platform on 8th floor
  109. 9th floor external & internal block masonry
  110. RCC patlee work
  111. External plaster 4th floor
  112. Placing junction box & conduit for 8th floor
  113. Chased part re-plastering
  114. Fixing Pre cast jalis 13th floor
  115. Internal plaster & toilet backing coat for 8th floor
  116. Interior cladding & flooring & polishing in lobbies on 3rd floor.
  117. Flooring & skirting in all rooms & kitchen excluding toilets of 6th floor.
  118. External plumbing G.I down takes AC/CI RWP & soil pipes (after external plaster in ducts) for Gr to 8th floor.
  119. Finishing of water proofing in toilets 1st floor
  120. Finishing of toilet plaster on 1st floor
  121. Finishing of water proofing in toilets 2nd floor
  122. Finishing of toilet plaster on 2nd floor
  123. Finishing of water proofing in toilets 3rd floor
  124. Finishing of toilet plaster on 3rd floor
  125. finishing of water proofing in toilets 4th floor
  126. Finishing of toilet plaster on 4th floor
  127. Finishing of water proofing in toilets 5th floor
  128. Finishing of toilet plaster on 5th floor
  129. Finishing of water proofing in toilets 6th floor
  130. Finishing of toilet plaster on 6th floor
  131. Finishing of water proofing in toilets 7th floor
  132. Finishing of toilet plaster on 7th floor
  133. External plaster 5th floor.
  134. fixing Pre cast jallies 14th floor
  135. 13th floor column beams slabs & all RCC items including ete. Conduit pipes, junction boxes, fan hooks sleeves etc.
  136. External plaster 6th floor
  137. Laying concealed traps etc 2nd floor
  138. Flooring & dado of toilets including polishing 2nd floor
  139. Fixing T.W. doors & windows shutter 2nd floor
  140. Kitchen platform on 9th floor
  141. 10th floor external internal block masonry
  142. Waterproofing of toilet/sumps on 4th floor
  143. 10th floor door frames fixing
  144. External plaster 7th floor
  145. Placing junction box & conduit of 9th floor
  146. Laying concealed traps etc 3rd floor
  147. Internal plaster & toilet backing coat for 9th floor
  148. Interior cladding & flooring & polishing in lobbies on 4th floor
  149. Flooring & skirting in all rooms & kitchen excluding toilets of 7th floor
  150. flooring & dado of toilets including polishing 3rd floor
  151. Fixing T.W. doors & windows shutters 3rd floor
  152. External drainage and construction of manholes.

Now you can download the complete sequence list of activities from below attachment.
 

Attachments

  • Sequence of construction activities.xls
    46 KB · Views: 2,132

Sachin Dhere

Apprentice
Very Useful information Sir
Thanks
May I know activities in mobilisation.
Mobilisation plan
How to start project with excavation activity?
Coordination with consultants
Lineout marking
Site infra setup
In detail checklist
 

Noman

Newbie
Hello Sir
Remember me.. I am SAYED NOMAN work with u in Thane for Arena project of Nakshatra Relators..

Very good information sir.
 
  • Like
Reactions: Apurv

Apurv

Newbie
hi all

i have identified the construction sequences through my experience. hope this will provide the fair idea of construction sequences of multistory building. suggestions and comment solicited.

regards
srinivsan
I am not able to download the attachment sir.
 

Papa

Newbie
Tha
Sequence of Construction Activities for Residential Building
When we work at a construction project, if sequencing of activity is not done, then the project may land up in trouble.
I had created a sequence of construction activities for one of may project of residential building in past.
It will also help you to track the activities for purchase, start and completion status.

The sequence of construction activities include following;
  1. Foundation (including excavation, anti-termite & de-watering) Footing
  2. Plinth beams (including earth filling compaction rubble soling)
  3. Grade slab (including Damp Proof course) with anti - termite
  4. 1st floor column beams, slabs & all RCC items staircase, lifts, etc including conceal conduit pipes, junction,s fan hooks, sleeves etc.
  5. Civil Work for U. G. Tank (suction & static & pump room)
  6. Placing order for lift & follow up.
  7. 2nd floor column beam slabs & all RCC items including conceal conduit pipes, junctions, fan hooks, sleeves etc.
  8. Manufacturing blocks
  9. Manufacturing door frames & window sub frames
  10. 3rd floor columns beam slab & all RCC items including conceal etc. conduit pipes, junction boxes, fan hooks, sleeves etc.
  11. Ground floor external & internal block masonry with door frames window & conduit pipe & boxes
  12. RCC patlee work in brick work
  13. 4th floor column beam slab & all RCC items with all conceal elc. Pipe work, junctions, fan hooks, sleeves etc.
  14. Fixing precast jallis on ground floor
  15. 1st floor external & internal block masonry
  16. Patlee in brick wall.
  17. 1st floor door & window frames fixing
  18. Ground floor junction box & conduit placing
  19. Internal cement plaster & backing coat (for toilets of Ground floor)
  20. Re-plastering conceal pipe chasing work
  21. 5th floor column beams slabs & all RCC items with etc. Pipe work & junctions, fan hooks, sleeves etc.
  22. 2nd floor external & internal block/ brick masonry
  23. RCC patlee work
  24. 2nd floor door & window frames fixing
  25. Re-plastering chasing part of conduit work
  26. 1st floor junction box & conduit placing.
  27. Internal cement plaster & toilet backing coat for 1st floor
  28. Re-plaster chess part of wall
  29. Fixing Pre cast jali 1st floor
  30. 6th floor column beams slabs & all RCC items including etc. Conceal conduits, junction boxes, fan hooks, sleeves etc.
  31. 3rd floor external & internal block masonry
  32. RCC patlee work
  33. 3rd floor door & window frames fixing
  34. Placing junction box & conduit for 2nd floor
  35. Re-plastering chasing part of wall
  36. Fixing Pre cast jali 2nd floor.
  37. Internal cement plaster & (toilet backing coat for 2nd floor
  38. Construction of kitchen platform 1st floor.
  39. Flooring & Skirting in all rooms & excluding toilets of Gr. floor
  40. Fixing Pre cast jali 3rd floor
  41. 7th floor column beams slabs & all RCC items including conceal etc. conduits, junctions, fan hooks, sleeves etc.
  42. 4th floor door & frames fixing
  43. 4th floor external & internal block masonry
  44. RCC patlee work
  45. Construction of kitchen platform on 2nd floor
  46. Placing junction box & conduit for 3rd floor
  47. Chased part re-plastering
  48. Fixing Pre cast jali 4th floor
  49. Internal plaster & toilet backing coat for 3rd floor
  50. Kitchen platform on 3rd floor
  51. Flooring & skirting in all room & kitchen excluding, toilets on 1st floor
  52. Fixing Pre cast jali 5th floor
  53. 8th floor column beams slabs & all RCC items including conceal etc. conduits, junction boxes, fan hooks & sleeves etc.
  54. 5th floor door frames fixing
  55. Kitchen platform on 4th floor
  56. 5th floor external & internal block masonry
  57. RCC patlee work
  58. Placing junction box & conduit for 4th floor
  59. Chased part re-plastering
  60. Fixing Pre cast jali 6th floor
  61. Internal plaster & toilet backing coat for 4th floor.
  62. Flooring & skirting in all rooms & kitchen excluding toilets of 2nd floor
  63. Fixing Pre cast jali 7th floor.
  64. 9th floor column beams slabs & all RCC items (7th floor plaster to be finished) including conceal conduit pipes, junction boxes, fan hooks sleeves etc.
  65. 6th floor door frames & window frames fixing
  66. Kitchen platform on 5th floor.
  67. 6th floor external & internal block masonry
  68. RCC patlee work
  69. Placing junction box & conduit for 5th floor.
  70. Chased part re-plastering
  71. Fixing Pre cast jali 8th floor.
  72. Internal plaster & toilet backing coat for 1st 5 floor.
  73. Internal marble granite cladding & flooring for lobbies including polishing on Ground floor
  74. Floor & skirting in all rooms & kitchen excluding toilets of 3rd floor.
  75. Waterproofing of toilets/sumps 1st floor 1st base coat
  76. 10th floor columns beams slabs & all RCC items including etc. Conduit pipes, junction boxes, fan hooks sleeves etc.
  77. 7th floor door frames fixing fixing
  78. Kitchen platform on 6th floor
  79. 7th floor external & internal block masonry
  80. RCC patlee work
  81. Placing junction box & conduit for 6th floor.
  82. Chased part re-plastering
  83. Fixing Pre cast jali 9th floor.
  84. Internal plaster & toilet backing coat for 6th floor.
  85. Interior cladding & flooring & polishing in lobbies on 1st floor.
  86. Flooring & skirting in all rooms & Kitchen excluding toilets of 4th floor
  87. External plaster ground to 8th floor
  88. Fixing Pre cast jali 10th floor.
  89. 11th floor column beams slabs & all RCC items including conceal etc. conduit pipes, junction boxes, fan hooks & sleeve etc.
  90. Waterproofing of toilets/sumps on 2nd floor, Base coat
  91. 8th floor door frames fixing
  92. Kitchen plat form on 7th floor
  93. 8th floor external & internal block masonry
  94. RCC patlle work
  95. Fixing Pere cast jali 11th floor
  96. Internal plaster & toilet backing coat for 7th floor
  97. Interior cladding & flooring & polishing in lobbies on 2nd floor.
  98. flooring & skirting in all room & kitchen excluding toilets of 5th floor
  99. External plaster on 1st floor
  100. Laying concealed traps etc including making holes in masonry for pipes from 1st flr.
  101. Flooring & dado of toilets including polishing from 1st floor.
  102. Fixing of T.W. doors & window shutter 1st floor
  103. Fixing Pre cast jali 12th floor.
  104. 12th floor column beams slabs & all RCC items including conceal etc. conduit pipes, fan hooks, junction boxes, sleeves etc.
  105. External plaster 3rd floor
  106. Waterproofing of toilets/sumps on 3rd floor Base coat
  107. 9th floor door frames fixing masonry
  108. Kitchen platform on 8th floor
  109. 9th floor external & internal block masonry
  110. RCC patlee work
  111. External plaster 4th floor
  112. Placing junction box & conduit for 8th floor
  113. Chased part re-plastering
  114. Fixing Pre cast jalis 13th floor
  115. Internal plaster & toilet backing coat for 8th floor
  116. Interior cladding & flooring & polishing in lobbies on 3rd floor.
  117. Flooring & skirting in all rooms & kitchen excluding toilets of 6th floor.
  118. External plumbing G.I down takes AC/CI RWP & soil pipes (after external plaster in ducts) for Gr to 8th floor.
  119. Finishing of water proofing in toilets 1st floor
  120. Finishing of toilet plaster on 1st floor
  121. Finishing of water proofing in toilets 2nd floor
  122. Finishing of toilet plaster on 2nd floor
  123. Finishing of water proofing in toilets 3rd floor
  124. Finishing of toilet plaster on 3rd floor
  125. finishing of water proofing in toilets 4th floor
  126. Finishing of toilet plaster on 4th floor
  127. Finishing of water proofing in toilets 5th floor
  128. Finishing of toilet plaster on 5th floor
  129. Finishing of water proofing in toilets 6th floor
  130. Finishing of toilet plaster on 6th floor
  131. Finishing of water proofing in toilets 7th floor
  132. Finishing of toilet plaster on 7th floor
  133. External plaster 5th floor.
  134. fixing Pre cast jallies 14th floor
  135. 13th floor column beams slabs & all RCC items including ete. Conduit pipes, junction boxes, fan hooks sleeves etc.
  136. External plaster 6th floor
  137. Laying concealed traps etc 2nd floor
  138. Flooring & dado of toilets including polishing 2nd floor
  139. Fixing T.W. doors & windows shutter 2nd floor
  140. Kitchen platform on 9th floor
  141. 10th floor external internal block masonry
  142. Waterproofing of toilet/sumps on 4th floor
  143. 10th floor door frames fixing
  144. External plaster 7th floor
  145. Placing junction box & conduit of 9th floor
  146. Laying concealed traps etc 3rd floor
  147. Internal plaster & toilet backing coat for 9th floor
  148. Interior cladding & flooring & polishing in lobbies on 4th floor
  149. Flooring & skirting in all rooms & kitchen excluding toilets of 7th floor
  150. flooring & dado of toilets including polishing 3rd floor
  151. Fixing T.W. doors & windows shutters 3rd floor
  152. External drainage and construction of manholes.

Now you can download the complete sequence list of activities from below attachment.
thanks Sir