The sequence of construction activities include following;
Now you can download the complete sequence list of activities from below attachment.
When we work at a construction project, if sequencing of activity is not done, then the project may land up in trouble.
I had created a sequence of construction activities for one of may project of residential building in past.
It will also help you to track the activities for purchase, start and completion status.
The sequence of construction activities include following;
- Foundation (including excavation, anti-termite & de-watering) Footing
- Plinth beams (including earth filling compaction rubble soling)
- Grade slab (including Damp Proof course) with anti - termite
- 1st floor column beams, slabs & all RCC items staircase, lifts, etc including conceal conduit pipes, junction,s fan hooks, sleeves etc.
- Civil Work for U. G. Tank (suction & static & pump room)
- Placing order for lift & follow up.
- 2nd floor column beam slabs & all RCC items including conceal conduit pipes, junctions, fan hooks, sleeves etc.
- Manufacturing blocks
- Manufacturing door frames & window sub frames
- 3rd floor columns beam slab & all RCC items including conceal etc. conduit pipes, junction boxes, fan hooks, sleeves etc.
- Ground floor external & internal block masonry with door frames window & conduit pipe & boxes
- RCC patlee work in brick work
- 4th floor column beam slab & all RCC items with all conceal elc. Pipe work, junctions, fan hooks, sleeves etc.
- Fixing precast jallis on ground floor
- 1st floor external & internal block masonry
- Patlee in brick wall.
- 1st floor door & window frames fixing
- Ground floor junction box & conduit placing
- Internal cement plaster & backing coat (for toilets of Ground floor)
- Re-plastering conceal pipe chasing work
- 5th floor column beams slabs & all RCC items with etc. Pipe work & junctions, fan hooks, sleeves etc.
- 2nd floor external & internal block/ brick masonry
- RCC patlee work
- 2nd floor door & window frames fixing
- Re-plastering chasing part of conduit work
- 1st floor junction box & conduit placing.
- Internal cement plaster & toilet backing coat for 1st floor
- Re-plaster chess part of wall
- Fixing Pre cast jali 1st floor
- 6th floor column beams slabs & all RCC items including etc. Conceal conduits, junction boxes, fan hooks, sleeves etc.
- 3rd floor external & internal block masonry
- RCC patlee work
- 3rd floor door & window frames fixing
- Placing junction box & conduit for 2nd floor
- Re-plastering chasing part of wall
- Fixing Pre cast jali 2nd floor.
- Internal cement plaster & (toilet backing coat for 2nd floor
- Construction of kitchen platform 1st floor.
- Flooring & Skirting in all rooms & excluding toilets of Gr. floor
- Fixing Pre cast jali 3rd floor
- 7th floor column beams slabs & all RCC items including conceal etc. conduits, junctions, fan hooks, sleeves etc.
- 4th floor door & frames fixing
- 4th floor external & internal block masonry
- RCC patlee work
- Construction of kitchen platform on 2nd floor
- Placing junction box & conduit for 3rd floor
- Chased part re-plastering
- Fixing Pre cast jali 4th floor
- Internal plaster & toilet backing coat for 3rd floor
- Kitchen platform on 3rd floor
- Flooring & skirting in all room & kitchen excluding, toilets on 1st floor
- Fixing Pre cast jali 5th floor
- 8th floor column beams slabs & all RCC items including conceal etc. conduits, junction boxes, fan hooks & sleeves etc.
- 5th floor door frames fixing
- Kitchen platform on 4th floor
- 5th floor external & internal block masonry
- RCC patlee work
- Placing junction box & conduit for 4th floor
- Chased part re-plastering
- Fixing Pre cast jali 6th floor
- Internal plaster & toilet backing coat for 4th floor.
- Flooring & skirting in all rooms & kitchen excluding toilets of 2nd floor
- Fixing Pre cast jali 7th floor.
- 9th floor column beams slabs & all RCC items (7th floor plaster to be finished) including conceal conduit pipes, junction boxes, fan hooks sleeves etc.
- 6th floor door frames & window frames fixing
- Kitchen platform on 5th floor.
- 6th floor external & internal block masonry
- RCC patlee work
- Placing junction box & conduit for 5th floor.
- Chased part re-plastering
- Fixing Pre cast jali 8th floor.
- Internal plaster & toilet backing coat for 1st 5 floor.
- Internal marble granite cladding & flooring for lobbies including polishing on Ground floor
- Floor & skirting in all rooms & kitchen excluding toilets of 3rd floor.
- Waterproofing of toilets/sumps 1st floor 1st base coat
- 10th floor columns beams slabs & all RCC items including etc. Conduit pipes, junction boxes, fan hooks sleeves etc.
- 7th floor door frames fixing fixing
- Kitchen platform on 6th floor
- 7th floor external & internal block masonry
- RCC patlee work
- Placing junction box & conduit for 6th floor.
- Chased part re-plastering
- Fixing Pre cast jali 9th floor.
- Internal plaster & toilet backing coat for 6th floor.
- Interior cladding & flooring & polishing in lobbies on 1st floor.
- Flooring & skirting in all rooms & Kitchen excluding toilets of 4th floor
- External plaster ground to 8th floor
- Fixing Pre cast jali 10th floor.
- 11th floor column beams slabs & all RCC items including conceal etc. conduit pipes, junction boxes, fan hooks & sleeve etc.
- Waterproofing of toilets/sumps on 2nd floor, Base coat
- 8th floor door frames fixing
- Kitchen plat form on 7th floor
- 8th floor external & internal block masonry
- RCC patlle work
- Fixing Pere cast jali 11th floor
- Internal plaster & toilet backing coat for 7th floor
- Interior cladding & flooring & polishing in lobbies on 2nd floor.
- flooring & skirting in all room & kitchen excluding toilets of 5th floor
- External plaster on 1st floor
- Laying concealed traps etc including making holes in masonry for pipes from 1st flr.
- Flooring & dado of toilets including polishing from 1st floor.
- Fixing of T.W. doors & window shutter 1st floor
- Fixing Pre cast jali 12th floor.
- 12th floor column beams slabs & all RCC items including conceal etc. conduit pipes, fan hooks, junction boxes, sleeves etc.
- External plaster 3rd floor
- Waterproofing of toilets/sumps on 3rd floor Base coat
- 9th floor door frames fixing masonry
- Kitchen platform on 8th floor
- 9th floor external & internal block masonry
- RCC patlee work
- External plaster 4th floor
- Placing junction box & conduit for 8th floor
- Chased part re-plastering
- Fixing Pre cast jalis 13th floor
- Internal plaster & toilet backing coat for 8th floor
- Interior cladding & flooring & polishing in lobbies on 3rd floor.
- Flooring & skirting in all rooms & kitchen excluding toilets of 6th floor.
- External plumbing G.I down takes AC/CI RWP & soil pipes (after external plaster in ducts) for Gr to 8th floor.
- Finishing of water proofing in toilets 1st floor
- Finishing of toilet plaster on 1st floor
- Finishing of water proofing in toilets 2nd floor
- Finishing of toilet plaster on 2nd floor
- Finishing of water proofing in toilets 3rd floor
- Finishing of toilet plaster on 3rd floor
- finishing of water proofing in toilets 4th floor
- Finishing of toilet plaster on 4th floor
- Finishing of water proofing in toilets 5th floor
- Finishing of toilet plaster on 5th floor
- Finishing of water proofing in toilets 6th floor
- Finishing of toilet plaster on 6th floor
- Finishing of water proofing in toilets 7th floor
- Finishing of toilet plaster on 7th floor
- External plaster 5th floor.
- fixing Pre cast jallies 14th floor
- 13th floor column beams slabs & all RCC items including ete. Conduit pipes, junction boxes, fan hooks sleeves etc.
- External plaster 6th floor
- Laying concealed traps etc 2nd floor
- Flooring & dado of toilets including polishing 2nd floor
- Fixing T.W. doors & windows shutter 2nd floor
- Kitchen platform on 9th floor
- 10th floor external internal block masonry
- Waterproofing of toilet/sumps on 4th floor
- 10th floor door frames fixing
- External plaster 7th floor
- Placing junction box & conduit of 9th floor
- Laying concealed traps etc 3rd floor
- Internal plaster & toilet backing coat for 9th floor
- Interior cladding & flooring & polishing in lobbies on 4th floor
- Flooring & skirting in all rooms & kitchen excluding toilets of 7th floor
- flooring & dado of toilets including polishing 3rd floor
- Fixing T.W. doors & windows shutters 3rd floor
- External drainage and construction of manholes.