The maximum deviation of the centre line of the foundations of a steel structure should be limited to -
(a) L / 100
(b) 1.1 sqrt(L)
(c) 10 mm
(d) L/10.
Where L = Span in Meter.
The correct Answer Is
(b) 1.1 sqrt(L)
(a) L / 100
(b) 1.1 sqrt(L)
(c) 10 mm
(d) L/10.
Where L = Span in Meter.
The correct Answer Is
(b) 1.1 sqrt(L)