The minimum number of days after which the formwork (including props) under the soffits of the beams can be stripped is -
(a) 3
(b) 7
(c) 10
(d) 14.
The correct Answer Is
(d) 14
(a) 3
(b) 7
(c) 10
(d) 14.
The correct Answer Is
(d) 14