The minimum number of days after which the soffit formwork of the slabs (excluding props) can be stripped is -

Dnyan Deshmukh

Eternal Member
Staff member
Sep 7, 2017
2,602
4,510
Pune
The minimum number of days after which the soffit formwork of the slabs (excluding props) can be stripped is -

(a) 2

(b)4

(c) 7

(d) 14.

Do reply with your answer and if possible add some description to your answer.

Once you reply, you can see the correct answer of the question, its really a fun game and learning.

Hidden content
You need to reply to this thread in order to see this content.
 
  • Like
Reactions: Sumit Civil

ENI2020

Newbie
May 18, 2020
6
1
Philippines
The minimum number of days after which the soffit formwork of the slabs (excluding props) can be stripped is -

(a) 2

(b)4

(c) 7

(d) 14.

Do reply with your answer and if possible add some description to your answer.

Once you reply, you can see the correct answer of the question, its really a fun game and learning.

[Hidden content]
d. 14 once the rest meets the required strength