Dnyan Deshmukh Staff member Pune Jan 18, 2018 #1 The minimum number of days after which the soffit formwork of the slabs (excluding props) can be stripped is - (a) 2 (b)4 (c) 7 (d) 14. The correct Answer Is (b)4 Reactions: Sumit Civil
The minimum number of days after which the soffit formwork of the slabs (excluding props) can be stripped is - (a) 2 (b)4 (c) 7 (d) 14. The correct Answer Is (b)4
ENI2020 Newbie Philippines May 22, 2020 #3 Dnyan Deshmukh said: The minimum number of days after which the soffit formwork of the slabs (excluding props) can be stripped is - (a) 2 (b)4 (c) 7 (d) 14. Click to expand... d. 14 once the rest meets the required strength
Dnyan Deshmukh said: The minimum number of days after which the soffit formwork of the slabs (excluding props) can be stripped is - (a) 2 (b)4 (c) 7 (d) 14. Click to expand... d. 14 once the rest meets the required strength