Model a schedule for the design and construction of a 4 story building in Dubai region. Include the following guidelines/points on scheduling

  • The project duration to be considered is 1.5 years.
  • Project should contain the activities from the signing of the contract to handover.
  • Make a WBS and list the detailed activities till Level 4.Proper relationships should be given to the activities.
  • Find the authority approvals to be considered while designing the building in Dubai region.
  • With the basic productivity chart find the quantity of resources required for Excavation and concreting works.
  • Assign the resources and export the Resource histogram chart.
  • Assign multiple calendars for Enterprise and Project, make sure the Ramadan timings are considered for the project.
  • Define the OBS structure for your organization ,submit a chart along with it
List the assumptions if any.
 