What is L2 and L3 Schedule? Can anyone provide me the appropriate format of L2 and L3 Schedule.

Dnyan Deshmukh

Staff member
From what i understood from your writing, it is Level 2 and Level 3 schedule.

There is only difference of time, cost management in it.

Level 2 schedule is for higher level of management (above Project Manager), it includes impact of time loss and catch up plan to achieve the final dates.

Level 3 is same schedule with a tighter dates for achieving goal so that it wont hamper level 2 schedule.

There are many issues are faced during execution of project and most of them due to miss communication or bad resource management.

So everybody had its own time limit to face the issues and deliver the product on time.

There is one more concept of schedule in it which i had seen in my previous company where they name it as S1 to S10 Schedules.
It represent plans for each component of project like, Material schedule, labour schedule, payment schedule, purchase schedule etc (Like a micro planning of each component in it).

As i am not working in planning department, i can not guide further more on this subject.