Aluminium Sliding Window Works
Aluminium window work is one of the most important work which is visible to all and it have good aesthetic values, if not executed correctly, it spoils the impression of company and make a bad impression on customers.
Checklist of Aluminium Sliding Window Works consist of following checkpoints in it;
Procedures to be followed before fixing
Procedures to be followed during fixing
Procedures to be followed after fixing of aluminium windows
Checklist is a important record it helps us in order to get work done correctly and it ensure we do not miss any point to check which is important from aspect of Quality of work.
Checklist attached herewith is just a sample provided for your reference, work carried out as per this procedure may have different sets of standards, material specifications, standard operating procedures and terms and conditions for doing that work. This all parameter or some parameter may not match with one you are executing at your Project.
Kindly use it as reference document only to create Checklist. You are free to modify edit, delete add any content in it and use it as per your requirement.
Aluminium window work is one of the most important work which is visible to all and it have good aesthetic values, if not executed correctly, it spoils the impression of company and make a bad impression on customers.
Checklist of Aluminium Sliding Window Works consist of following checkpoints in it;
Procedures to be followed before fixing
- Material checked as specified (variation in wt. not more than +/-10%)
- Necessary drawing showing details of AC ,exhaust fan, mosquito net location, aluminium sections available
- Gypsum, Plaster, Tiling and jambs of windows completed to satisfaction(plumb, level, line, plain)
- Window sill outside of Aluminium frame given outward slope
Procedures to be followed during fixing
- Horizontal and vertical members joined at 45º and joint kept hairline
- Tracks checked for numbers and defects
- Distance of frame from corner of jambs checked (before fixing)
- Holes drilled in bottom member for fixing screws as specified ( for reference; approximately 300mmc/c for bottom and for sides / top members at 450 mmc/c )
- Shutters checked for sizes, straightness, diagonal distances and plumb (shutter should be exactly rectangle or square)
- Anodizing/ Powder coating checked for color, thickness and scratches
- PVC gasket, Wool pile packing checked for air tightness after fixing
- Glass shade and thickness as per specification
- Glass sizes checked and roller bearings fixed as specified (min.2 bearings per shutter)
- Hardware fittings such as locks, handles, screws, pivots of approved make(as specified)
- Drain holes minimum 2 nos. per shutter at the bottom track for easy draining of water outside
Procedures to be followed after fixing of aluminium windows
- Aluminium sections covered with masking tape after installation
- Gaps between sections and plaster(externally ) filled with sealant of matching color
- Gaps between sections and plaster(internally) filled with putty (or recommended material)
- Window frame bottom cleaned with air blower
- Shutters after closing checked for air tightness (smooth operation without rattling noise)
- Bottom track checked for proper draining of water
Checklist is a important record it helps us in order to get work done correctly and it ensure we do not miss any point to check which is important from aspect of Quality of work.
Checklist attached herewith is just a sample provided for your reference, work carried out as per this procedure may have different sets of standards, material specifications, standard operating procedures and terms and conditions for doing that work. This all parameter or some parameter may not match with one you are executing at your Project.
Kindly use it as reference document only to create Checklist. You are free to modify edit, delete add any content in it and use it as per your requirement.