what if slump test fails at site condition what to do as site engineer in that situatuion .
like what if slump comes more than +/- 20
what to do if it is more and what to do when its less
what to do in case of collapseable slump and shear slump
when to reject concrete based on slump
Fresher. I had undergone training in design of R. C.C structure as per Indian standard. I like to work as a site engineer to gain some knowledge in site
Attached my cv
1. Types of drawing.
2. Site work (checking & managing).
3. Material management.
4. Estimation and billing.
This post is only on Types of drawing should an engineer look for.
Types of Drawing:-
Architectural Drawings
Structural Drawings
Demarcation plan
Footing& Column Drawing
Working...
Site Engineer should check this in Reinforcement Steel work
Engineers who are working at construction project and actually look after the construction activities going at project, should check the following points during Reinforcement steel works.
Before starting reinforcement work formwork...
In general below activities are overlooked by a Site Engineers and Supervisors. This may cause a serious trouble to the structure during earth quakes.
Ring / Stirrup hooks not bent at 135 degree.
The studies shown that, during earthquake a hook bent at 90 degree opens out and structure fall...