Finishing activities sequence

kulkarni

Junior Member
1) chasing work for plumbing, electrical.
2) plumbing & electrical pipes fixing and finishing.
3) water proofing work in toilets, balcony and utility.
4) sewer lines fixing in toilets, balcony and utility.
5) pressure testing for plumbing in toilets and utiity.
6) door frame for main door, internal, toilet and utility
7) internal plaster of toilets and utility.
8) external plaster for outside walls
9) dado and flooring work in toilets, utility and balcony.
10) gypsum wall punning work in all rooms.
11) tile flooring and skirting work in all rooms.
12) window sill and kitchen granite fixing work.
13) corridor floor and skirting tile fixing.
14) lift m.s frame fixing.
15) staircase granite fixing.
16)window frames and shutter fixing.
17) wiring switch box fixing.
18) internal painting work.
19) external plumbing work.
20) balcony and staircase railing work.
21) terrace water water line work.
22) terrace and water tank water proofing work.
23) drinking, solar water line fixing and testing.
24) chamber work for plumbing in parking.
25) external painting work.
26) parking tile fixing.
28) lift wiring work.
29) lift installation and testing.
30) door shutter fixing.
31) toilet false ceiling work.
32) commode and cp sanitary fitting fixing also door fitting fixing.
33) corridor and staircase painting work.
34) m.s gate fixing.
35) staircase and parking lighting work.
36) parking, gate and compund wall painting work
37) flats cleaning and handing over.
 