Hi all,
Here I want to share my experience in the recent past...
When you want to take pending works for various works what you will Do?
Prepare an excel format like I am taking pending works of ventilator,I formed a table in excel stating the location A block 001 flat ventilator of size .45x.60m is pending leave the status as blank
002 flat ventilator done put tick mark
In the result column put a formula =sumblank(A3:A5)
The blank cells will be counted
Multiply the area and the number of blank cells give the pending area
Hope it will be useful
Soon I will update an excel sheet as an example
Here I want to share my experience in the recent past...
When you want to take pending works for various works what you will Do?
Prepare an excel format like I am taking pending works of ventilator,I formed a table in excel stating the location A block 001 flat ventilator of size .45x.60m is pending leave the status as blank
002 flat ventilator done put tick mark
In the result column put a formula =sumblank(A3:A5)
The blank cells will be counted
Multiply the area and the number of blank cells give the pending area
Hope it will be useful
Soon I will update an excel sheet as an example