Quality Assurance Plan

Quality Assurance Plan (QAP)
QAP is the document which shows the sequence of Quality Control system (QCS) including frequency and numbers of tests based on the detail work program.

QAP generally presented by the contractor against the specification of the Employer/Client during the signing of the contract. QAP is the basic document to control the quality of works for contractor which also help the client/consultant for the supervision of the quality.

QAP contains the following

a) Quality Control Schedule
- test schedule
- testing program
- list of tests
- laboratory; site trials & trial sections
- construction control test & its frequencies
- numbers of tests to be carried out & list of equipment to conduct them
- list of “critical” acceptance testing procedures
- list of staff assigned to the laboratory, their position & responsibilities

b) List of sources of materials and/or of manufactured articles



Quality Assurance Plan for the construction materials from Natural resources


S.NOMaterial DescriptionSpecification reference page no. or clause no.Quantity as per BOQName of the tests to be carried outFrequency of TestNos. of test to be carried out as per the specificationRemarks
RequiredCarried OutCompliance
1AggregateGradationFrom each quarry source one set of tests
LAA
Water Absorption
FI
2aSand for Concrete worksGradationFrom each quarry source one set of tests
2bSand for Masonry worksGradationFrom each quarry source one set of tests
3StoneWater AbsorptionFrom each quarry source one set of tests
Specific Gravity
4Filter MaterialGradationEvery 50 m3 - 1 set of tests
5Soil for embankmentCompactionEvery 1500 m3 - 1 set of tests
Field Density500 m2 one nos of tests
6Subgrade PreparationCompactionEvery 3000 m2 - 1 set of tests
Field Density500 m2 one nos of tests


Quality Assurance Plan for the construction materials (Factory Manufactured)

S.NOMaterial DescriptionManufacture's Certificate Received & ApprovedSpecificationQuantity as per BOQName of the tests to be carried outFrequency of TestNos. of test to be carried out as per the specificationRemarks
RequiredCarried OutCompliance
1Cement614377186Initial settingFor each 200 tons 1 set of tests on each supply2
Final setting2
Compressive strength2
test, 3 days2
7 days2
2Gabions63337,867.22Mass of zinc coatingupto 25 nos of coils 2 nos sampling,
Adhesion test *26 to 50 nos of coils-3 nos sampling
Uniformity test *51 to 150 nos of coils - 5 nos sampling
Tensile trest151 to 3000 nos of coils-8 nos sampling
above 300 nos of coils - 13 nos sampling
2Geotextile6273,383.60
3Steel6206.68Tensile strengthEach lot1
Elongation1


QUALITY ASSURANCE PLAN (QAP) Sample (for a road construction project)
BoQ Item
No.
Specification Clause Ref.Description of worksQuantity as per BoQUnitTest RequiredFrequency of test *Total no of Test Required as per BOQManagement of TestsRemarks
EquipmentAt (Site/Lab/Others)By
Embankment Fillingm31.Gradation1inm3
2.LL-PI1 inm3
3.MDD & OMC1 inm3
4. Field Density1 inm2
5. CBR
Sub grade Preparationm21.LL-PI1 inm2
2.MDD & OMC1 inm2
3. Field Density1 inm2
4. CBR1 inm2
Supply and laying of Granular Subbasem31. Gradation1 inm3
2.LL- PI1 inm3
3. MDD & OMC1 inm3
4. Soaked CBR1 inm3
5. Field density1 inm2
 