Dnyan Deshmukh Staff member Pune Jan 18, 2018 #1 The minimum number of days after which the formwork on the sides of beams can be stripped is - (a) 1 (b) 5 (c) 10 (d) 14. The correct Answer Is (a) 1 Reactions: Sumit Civil
The minimum number of days after which the formwork on the sides of beams can be stripped is - (a) 1 (b) 5 (c) 10 (d) 14. The correct Answer Is (a) 1
Ggf Newbie Kutch May 21, 2020 #2 Dnyan Deshmukh said: The minimum number of days after which the formwork on the sides of beams can be stripped is - (a) 1 (b) 5 (c) 10 (d) 14. Click to expand... 14
Dnyan Deshmukh said: The minimum number of days after which the formwork on the sides of beams can be stripped is - (a) 1 (b) 5 (c) 10 (d) 14. Click to expand... 14
Ajaikrishnan Newbie Kerala May 21, 2020 #3 14 Dnyan Deshmukh said: The minimum number of days after which the formwork on the sides of beams can be stripped is - (a) 1 (b) 5 (c) 10 (d) 14. Click to expand... 14
14 Dnyan Deshmukh said: The minimum number of days after which the formwork on the sides of beams can be stripped is - (a) 1 (b) 5 (c) 10 (d) 14. Click to expand... 14
V V R Suresh Simha Junior Member Bengaluru May 21, 2020 #4 Dnyan Deshmukh said: The minimum number of days after which the formwork on the sides of beams can be stripped is - (a) 1 (b) 5 (c) 10 (d) 14. Click to expand... 1
Dnyan Deshmukh said: The minimum number of days after which the formwork on the sides of beams can be stripped is - (a) 1 (b) 5 (c) 10 (d) 14. Click to expand... 1
ENI2020 Newbie Philippines May 22, 2020 #5 Dnyan Deshmukh said: The minimum number of days after which the formwork on the sides of beams can be stripped is - (a) 1 (b) 5 (c) 10 (d) 14. Click to expand... a 1 day