Dnyan Deshmukh Staff member Pune Jan 18, 2018 #1 The minimum number of days after which the soffit formwork of the beams (excluding props) can be stripped is - (a) 21 (b) 14 (c) 7 (d) 3. The correct Answer Is (c) 7 Reactions: HockeyPuck and Sumit Civil
The minimum number of days after which the soffit formwork of the beams (excluding props) can be stripped is - (a) 21 (b) 14 (c) 7 (d) 3. The correct Answer Is (c) 7
R rashi Newbie Jaipur Apr 5, 2019 #3 Dnyan Deshmukh said: The minimum number of days after which the soffit formwork of the beams (excluding props) can be stripped is - (a) 21 (b) 14 (c) 7 (d) 3. Click to expand... 7 days
Dnyan Deshmukh said: The minimum number of days after which the soffit formwork of the beams (excluding props) can be stripped is - (a) 21 (b) 14 (c) 7 (d) 3. Click to expand... 7 days
Rushal Newbie Goa Apr 5, 2019 #5 Dnyan Deshmukh said: The minimum number of days after which the soffit formwork of the beams (excluding props) can be stripped is - (a) 21 (b) 14 (c) 7 (d) 3. Click to expand... 14
Dnyan Deshmukh said: The minimum number of days after which the soffit formwork of the beams (excluding props) can be stripped is - (a) 21 (b) 14 (c) 7 (d) 3. Click to expand... 14