Work Method Statement for Plastering and Pointing on the Masonry
SCOPE/PURPOSE
This procedure covers the methodology to be followed for carrying out plastering and pointing work over the masonry in line with the approved technical specifications.
CODES / SPECIFICATION
IS 1661
RESPONSIBILITY
Responsibilities of all concerned is clearly mentioned with respect to overall administration and implementation in the approved Organogram.
MATERIALS TO BE USED
Cement, Sand, Water, Chicken mesh, Waterproofing compound.
SAFETY REQUIREMENT Safety in Plastering and pointing:
As per the requirement and the direction of Project Manager.
DEPLOYMENT OF LABOUR
As per the requirement and the direction of Project Manager.
IMPLEMENTATION
Preparatory Works (Before Taking up Plastering): Work Preparation.
Complete all internal / external works like
Do prepare the surface to be plastered by
SCOPE/PURPOSE
This procedure covers the methodology to be followed for carrying out plastering and pointing work over the masonry in line with the approved technical specifications.
CODES / SPECIFICATION
IS 1661
RESPONSIBILITY
Responsibilities of all concerned is clearly mentioned with respect to overall administration and implementation in the approved Organogram.
MATERIALS TO BE USED
Cement, Sand, Water, Chicken mesh, Waterproofing compound.
SAFETY REQUIREMENT Safety in Plastering and pointing:
- Use double scaffolding always and ensure the scaffolding is adequately braced with the permanent structure, for working in heights.
- Ensure the workers use safety appliances like safety belts in height, helmets, safety goggles while carrying out chipping etc while carrying out plastering and pointing in heights.
- Ensure the working area is kept clean for easy access and protect edges of opening by barricading etc while working.
- Ensure the area of working is well lighted (provided with lights) so that work area is easily accessed and moved around safely by workers.
- Inspect the scaffolding before starting work.
- Access platform/working platform double hand railing to be provided.
- Proper illumination to be provided during the work, if required.
- Educate the workmen through pep-talk meeting.
As per the requirement and the direction of Project Manager.
DEPLOYMENT OF LABOUR
As per the requirement and the direction of Project Manager.
IMPLEMENTATION
Preparatory Works (Before Taking up Plastering): Work Preparation.
Complete all internal / external works like
- Filler walls in structural frame work
- Fixing frames of doors, windows and ventilators
- RCC pre-cast jali works,
- Fixing and concealing all kinds of pipes (getting concealed in the walls)
- Complete all pipelines works to their final positions and levels for Water supply lines, Sewer pipelines, Telephone conduits, Electrical conduits, TV Antenna lines & piping work for other services if any coming on wall surfaces to be completed with their hood covers fixed and finished to the final surface level of the walls / ceilings.
- All lightning protection like earthing to be completed.
Do prepare the surface to be plastered by
- Clearing all dirt and loose matter
- Chipping and clearing of mortar dropping.
- Chipping and clearing of unevenness in the masonry, concrete works in ceiling and walls of rooms.
- Chipping and clearing the debris in areas of skirting and dado after marking the cutoff levels clearly.
- Raking out joints if necessary for proper keying