Factors that affects the concrete quantity in practical application.
Yield of the concrete = it is like after mixing ingredients as per design, do am i getting volume of concrete equals to 1 cum or is there any difference.
This volume gets affected due to change in source of the aggregates, if aggregates becomes lighter in density, your concrete is going to give you more than a cum in volume for same mix design. it will further reduce the volume of the concrete in case of aggregates received are heavier than one used for doing mix design.
Batching Error - The batching plant if looses its calibration on its weight scales, it will impact severely on a produce concrete like it will overdose the aggregates in a mix which will tend to increase the volume of 1 cum of concrete with same cement content.
Error in Theoretical Concrete Quantity Calculations - This will also lead to difference between poured and theoretical quantity either on plus or on minus side.
Pouring Error - In case of the mass concrete pouring less by few mm or few cm could make a huge difference in the concrete quantity which in most of the cases results in consumption of concrete by less than required amount as per theoretical value.